Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$715,657.50
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: September 21, 2018
Ready for final payment: October 6, 2018
Net changes from previous Change Orders
$0.00
Net change from previous Change Orders
Substantial completion: September 21, 2018
Ready for final payment: October 6, 2018
Contract Price prior to this Change Order
$715,657.50
Contract Times prior to this Change Order
Substantial completion: September 21, 2018
Ready for final payment: October 6, 2018
Net Increase (deerease} of this Change Order
$119,989.50
Net Increase eerease} of this Change Order
Substantial completion: 70 calendar days
Ready for final payment: 85 calendar days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$835,647.00 Substantial completion: December 16, 2018
Ready for final payment: December 31, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: | By: By
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature)
(Authorized Signature)
Date:
(Authorized Signature)
Date:
Change Order # 1
2018 CIPP Lining
2 of 2