Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$6,727,834
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 15, 2018
Ready for final payment: October 31, 2018
Net changes from previous Change Orders
$50,600
Net change from previous Change Orders
NONE
Contract Price prior to this Change Order
$6,777,834
Contract Times prior to this Change Order
Substantial completion: October 15, 2018
Ready for final payment: October 31, 2018
Net Increase decrease} of this Change Order
$359,738
Net Increase decrease} of this Change Order
60 calendar days
Contract Price with all approved Change Orders
$ 7,137,572
Contract Times with all approved Change Orders
Substantial completion: December 15, 2018
Ready for final payment: December 31, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: By:
By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order # 2 3 of 3
2018 Paving Program