CHANGE ORDER
No. 2
PROJECT: 2018 Paving Program
OWNER’S CONTRACT NO: IFB0660-040518
EXECUTED CONTRACT DATE: _ May 14, 2018
DATE OF ISSUANCE: July 5, 2018 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 141290
CONTRACTOR: Newport Construction Corp.
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Change Order #2 is for
2
An increase for charges associated with increased demand of Flaggers for the 2018 Paving
Program in the amount of $100,000
An increase for the treatment method change from mill and overlay to reclaim in the amount of
$70,658
An increase in Allowance for Liquid Asphalt Adjustment in the amount of $165,000
An increase to widen Charron Avenue to address ongoing traffic back-up issues in the amount
of $24,170
TOTAL NET CHANGE: $359,738
Change Order # 2 1 of 3
2018 Paving Program