CHANGE IN CONTRACT PRICE:
Original Contract Price
$414,265.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Final completion: September 1, 2018
Net changes from previous Change Orders
$9,874.00
Net change from previous Change Orders
Final completion: September 1, 2018
Contract Price prior to this Change Order
$424,139.00
Contract Times prior to this Change Order
Final completion: September 1, 2018
Net Increase (deerease} of this Change Order
$40,000.00
Net Increase (deerease} of this Change Order
60 calendar days
Contract Price with all approved Change
Orders
Contract Times with all approved Change Orders
$464,139.00 Final completion: November 1, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: By:
By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #2 2 of 2
2018 Sidewalk Program