CHANGE ORDER
No. 02
PROJECT: 2018 Sidewalk Program
OWNER’S CONTRACT NO: IFB0660-040518
EXECUTED CONTRACT DATE: _ May 14, 2018
DATE OF ISSUANCE: ___ Sept. 6, 2018 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 140991
CONTRACTOR: Leighton A. White
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
Change Order #2 is for additional costs associated with the imcrease in quantities to increase in the
scope of work. The work includes curbing, detectable warning panels, concrete and bituminous
sidewalk as well as traffic control. Revised Bid Quantities are attached
The Amherst Street & Broad Street Sidewalk Repairs project involves the reconstruction of pedestrian
sidewalk ramps for ADA compliance along Amherst Street (between Somerset Parkway and Broad
Street) and Broad Street (Between Broadcrest Lane and Amherst Street). Improving these ramps is
required in order to use federal funds for the paving of Amherst Street/Somerset Parkway and Broad
Street. During the review process of the paving plans of the arterial streets (Amherst Street, Somerset
Parkway, Broad Street, and Kinsley Street), New Hampshire Department of Transportation (NHDOT)
pointed out the need to repair additional sidewalk ramps, which are close to the project limits.
Change Order #2 1 of 2
2018 Sidewalk Program