Bier KELEY Exhibit B: Scope of Work
BULLDING
CloMPAaNy and Associated Fees
14 Court Street Building Renovations - RFQ 0745-072018
We are pleased to submit the following proposal for 14 Court Street for your review. Per the walk-through clarifications and
written scope of work we list the following.
Electrical
e 9 LED surface mounted lights (1) one per unit with associated wall switch.
e 2 Duplex outlets per unit, total 18
® 2convenience duplex outlets at “Open area for Activities and Displays”
e Keep existing lighting for general purpose lighting.
o Total $5,893.00
Life Safety
e 1 EBU emergency light fixture
1 Illuminated Exit Sign
Program and install 1 horn strobe
Program and install 1 pull station at egress
1 #10 ABC fire extinguisher at egress
Replace with updated Sprinkler Heads if required by NFD
o Total $1,988.00
Carpentry and Finishes
e Frame and board per drawings and specifications 9 units, along with secured access area and 3 unit closet storage
area, per direction at walk-through.
e Install prehung hollow core doors with storage locks.
e 2 Wood framed metal wire gates to secure rear elevated storage area as discussed in the walk-through.
e = Install 13 prehung doors
© 9 for artist units
o 3 for closet area
o 1 atsecure area at water heater
® Install custom metal ladder in secure area for access to elevator machine room as suggested during walkthrough.
Vinyl base at all new walls
e 1 coat prime and 2 coats paint all new walls and doors
o =Total $29,228.00
Plumbing
e Connect existing sink into the janitor’s closet. Assuming all piping in this area is accessible and able to accept
normal installation connections.
o Total $1,000.00
General Conditions including Performance Bond, final cleaning, dumpsters and fees.