DF
SALES CONFIRMATION
Fixed + Secure
This Sales Confirmation supplements, forms a part of and is expressly subject to that certain Master Retail Electricity
Sales Agreement (the “Master Agreement’) dated October 25, 2018, as may be amended from time to time, (which is
incorporated herein for all purposes, and along with this Sales Confirmation, is collectively referred to as the “Agreement”)
between City of Nashua (‘Buyer’) and EDF Energy Services, LLC, (‘Seller’) (Buyer and Seller may be individually
referred to as “Party” or collectively as “Parties”), the Parties have agreed to transact as set forth below. Terms that are
capitalized but not otherwise defined in this Sales Confirmation shall have the meaning(s) ascribed to such terms in the
Master Agreement or as defined in the applicable ISO tariff. In the event of inconsistency between the terms of this Sales
Confirmation and the terms of the Master Agreement, the terms and conditions of the Sales Confirmation shall prevail.
Sales Confirmation Effective Date: October 25, 2018
Start Date: The Service Start Date shall be the utility meter read occurring on or about November 1, 2018
End Date: The Service End Date shall be the utility meter read occurring on or about November 1, 2020
Term: 24 Months
Pricing: Buyer will pay, for any Usage during the Term, an amount equal to (1) Metered Usage multiplied by the Contract
Price (or the Transition Price, if applicable), (2) charges associated with Pricing Components marked with a “P” in Figure
1 and (3) any Other Charges not included in the Contract Price and specified in this Sales Confirmation
Contract Price: The Contract Price shall be $86.70 per MWh.
Price Components: As shown in Figure 1, Buyer shall be invoiced on a pass-through basis for those Price Components
that are marked with a “P”. Price Components marked with an “F” shall be included in the Contract Price.
Figure 1:
Energy Charge
Capacity Charge
Line Losses and UFE
Locational Forward Reserve (“LFR”)
Reliability Must Run (“RMR”)
Ancillary & Settlement Charges/Credits
Renewable Portfolio Standards Charge (“RPS”)
THT TEE TT) PE TT
The Contract Price does not include the following items (“Other Charges”) which will be Passed Through:
1. DSP charges and credits invoiced to Seller by the applicable DSP for each Delivery Point.
2. All taxes and assessments imposed on the retail sales of electricity, including sales tax, reimbursement for
miscellaneous gross receipts taxes and reimbursement for PUC assessment fee. This shall include all federal, state,
municipal and local taxes, duties, fees or other charges imposed on Seller by any governmental authority, directly
or indirectly, with respect to the electricity and other related products and services provided by Seller to Buyer’s
Service Accounts including any taxes enacted after the Effective Date.
Generai Definitions
1. Ancillary & Settlement Charges/Credits - Applicable charges and/or credits for ancillary services and other ISO
charges and credits as set forth in the applicable ISO Tariff and for other ISO costs not otherwise included in any of
the defined cost components set forth herein. Applicable Ancillary Service Charges will be allocated based on
Buyer's $/MWh share of Seller's total portfolio costs for Ancillary Services.
Capacity Charge — A charge for fulfilling resource adequacy requirements imposed by the ISO or otherwise.
ISO — iSO means the applicable Independent System Operator.
Line Losses and UFE — The applicable transmission and distribution losses plus unaccounted for energy as
published by the ISO or DSP as applicable.
EDFES CONFIDENTIAL Std ISONE Fixed+Secure Sales Confirm_Rev. Jun-01-2018v1.0