Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$1,139,300
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: September 3, 2018
Ready for final payment: October 1, 2018
Net changes from previous Change Orders
30
Net change from previous Change Orders
Substantial completion: Same as above
Ready for final payment: Same as above
Contract Price prior to this Change Order
$1,139,300
Contract Times prior to this Change Order
Substantial completion: Same as above
Ready for final payment: Same as above
Net Increase (deerease} of this Change Order
$27,000
Net Increase (deerease} of this Change Order
Substantial completion: 102 calendar days
Ready for final payment: 225 calendar days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$1,166,300 Substantial completion: December 15, 2018
Ready for final payment: January 30, 2019
RECOMMENDED: ACCEPTED: APPROVED:
By By:
By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #1 2 of 2
2018 Sewer Rehab
Kinsley Street