Summary
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Times
Original Contract Price
$3,987,518.90
Substantial completion: October 5, 2018 (Kinsley St)
Substantial completion: Nov 12, 2018 (Amherst & Somerset)
Substantial completion: June 28, 2019 (Broad St )
Ready for final payment: July 30, 2019
Net changes from previous Change Orders
$0
Net change from previous Change Orders
Substantial completion: Same as above
Ready for final payment: Same as above
Contract Price prior to this Change Order
$3,987,518.90
Contract Times prior to this Change Order
Substantial completion: Same as above
Ready for final payment: Same as above
Net Increase (deerease} of this Change Order
$611,547.75
Net Increase (deerease} of this Change Order
206 calendar days (Kinsley St)
225 calendar days (Amherst & Somerset)
0 calendar days (Broad St )
Ready for final payment: 0 calendar days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$4,599,066.65 Substantial completion: May 1, 2019 (Kinsley St)
Substantial completion: April 24, 2019 (Amherst & Somerset)
Substantial completion: June 28, 2019 (Broad St )
Ready for final payment: July 30, 2019
RECOMMENDED: ACCEPTED: APPROVED:
By: By:
By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #1 2 of 2
2018 Federal Paving Program