Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$6,727,834
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 15, 2018
Ready for final payment: October 31, 2018
Net changes from previous Change Orders
$409,738
Net change from previous Change Orders
Substantial completion: December 15, 2018
Ready for final payment: December 31, 2018
Contract Price prior to this Change Order
$7,137,572
Contract Times prior to this Change Order
Substantial completion: December 15, 2018
Ready for final payment: December 31, 2018
Net Increase (decrease) of this Change Order
$209,180
Net Increase (deerease} of this Change Order
NONE
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$ 7,346,752 Substantial completion: December 15, 2018
Ready for final payment: December 31, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: By:
By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #3 2 of 2
2018 Paving Program