Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$692,905.20
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: 60 days from NTP
Ready for final payment: 74 days from NTP
Net changes from previous Change Orders
$0.00
Net change from previous Change Orders
Substantial completion: n/a
Ready for final payment: n/a
Contract Price prior to this Change Order
$692,905.20
Contract Times prior to this Change Order
Substantial completion: n/a
Ready for final payment: n/a
Net Increase of this Change Order
$440,037.16
Net Increase (deerease} of this Change Order
Substantial completion: see below
Ready for final payment: see below
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$1,132,932.30 Substantial completion: Jume 30, 2019
Ready for final payment: July 36, 2019
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By: .
DPW Northeast Earth Mechanics, LLC Mayor Jim Donchess
Engineer (Authorized Signature) Owner
(Authorized Signature) (Authorized Signature)
Date:
Date: Date:
Change Order # 2 2 of 2
2018 Sewer Replacement — Harvard St.