  2. Finance Committee - Agenda - 12/5/2018 - P48

Finance Committee - Agenda - 12/5/2018 - P48

By dnadmin on Mon, 11/07/2022 - 11:25
Document Date
Fri, 11/30/2018 - 13:06
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 12/05/2018 - 00:00
Page Number
48
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__120520…

Summary

CHANGE IN CONTRACT PRICE:
Original Contract Price

$692,905.20

CHANGE IN CONTRACT TIMES:
Original Contract Times

Substantial completion: 60 days from NTP
Ready for final payment: 74 days from NTP

Net changes from previous Change Orders

$0.00

Net change from previous Change Orders

Substantial completion: n/a
Ready for final payment: n/a

Contract Price prior to this Change Order

$692,905.20

Contract Times prior to this Change Order

Substantial completion: n/a
Ready for final payment: n/a

Net Increase of this Change Order

$440,037.16

Net Increase (deerease} of this Change Order

Substantial completion: see below
Ready for final payment: see below

Contract Price with all approved Change Orders

Contract Times with all approved Change Orders

$1,132,932.30 Substantial completion: Jume 30, 2019
Ready for final payment: July 36, 2019
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By: .
DPW Northeast Earth Mechanics, LLC Mayor Jim Donchess
Engineer (Authorized Signature) Owner
(Authorized Signature) (Authorized Signature)
Date:
Date: Date:
Change Order # 2 2 of 2

2018 Sewer Replacement — Harvard St.

Page Image