Bid Item No. 4 Survey
This item requires that CONTRACTOR provide all labor and equipment required to perform
construction layout and as-built decumentation as required by the Drawings and as requested by
ENGINEER and/or OWNER. Construction layout shall be completed prior to the start of screened till
placement and shall include the concrete block wall alignment and all other work items as defined in
the Drawings. CONTRACTOR shall document the constructed alignment of the concrete block wail.
As-built survey locations shall be performed as features are constructed for payment and record
information and shall include all completed items as defined in the Drawings. This item will be paid on
a lump sum basis prorated over the scheduled duration of the work.
Page 3 of 4