op Project Lead Project Staff Lead Staff Direct labor
Task Descriptions Manager Engineer Engineer Designer Designer Admin Total Hours | Non-Labor Cost TOTAL
Typical Salary Rate $74 $52 $32 $40 $33 $24
Summary by Task for 5700 Form:
1. Pre-Con Services 12 0 16 0 0 0 28 $1,400 $4,060.00
2. Construction Observation 34 72 0 0 0 0 106 $6,260 | $18,154.00
3. RFE & Submittal Review 2 16 48 0 0 0 66 $2,516 $7,296.40
4. Startup and Commisssioning 10 58 112 0 0 4 184 $3,200 $7,424 | $24,729.60
5.Project Closeout 6 22 102 0 0 20 150 $5,272 | $15,288.80
TOTAL HOUR 64 168 278 0 0 24 534 $22,872 $69,529
$4,736 $8,736 $8,896 $0 $0 $504 Direct Labor $22,872
Indrect labor $43,457
Non-Labor $600
Subcontractor $3,200
Sub Markup $0
Fixed Fee $6,633
TOTAL Fee $76,762