City of Nashua Waste Water Treatment Facility — Energy Recovery Generator Upgrade
Construction Administration
Clarifications
1. Emission and other Environmental tests by others.
2. Load bank, if needed, by others.
3. Digested gas quality and quantity is managed by NWWTE and meet the engine
generator minimum standards. During startup and commissioning, Waldron expected
there is sufficient digested gas to operate minimum one new engine generator at any
given time.
4. Factory Acceptance Test is not included.
5. Waldron is not responsible for Warranty period for specific equipment and
components.
6. Waldron estimate uninterrupted, continuous commissioning and testing period will
last 4 weeks.
7. -No performance test is included.
8. Red-line drawings and As-built document and electronic files will be provided by
others.
9. All protection relay setting, programming, installation and third party
verification would be by others.
10. Noise Testing of completed project not included
11. Material delays or suspension in the continuous progression of the
Commissioning work which is beyond the reasonable control of Waldron will be
subject to delay and or remobilization charges. Waldron proposes to enter into
discussion with NWWTF in the development of a revised commissioning
schedule and, as a part of that process, reasonable durations for the work will
be determined and become the reference baseline for any delay or suspension.
a) In the event of such a delay, time extensions will be invoiced at Time and Material
Basis. Waldron’s rate schedule is attached for your reference.