1.
wt
Update CAD drawings “for Record” based on contractor provided red-line markup.
Revision for equipment markup will be by equipment vendors.
Review major equipment O&M manuals for completeness and accuracy
Review and comment on spare parts inventories. Make recommendations regarding
specific parts and quantities to be kept on hand
Review and comment on service contracts. Make recommendations regarding
adequacy of contracts in place and frequency of service.
Review equipment warranties to ensure Owner's responsibilities are clearly defined.
Compile a Systems Operations Manual that consists of the following: design narrative
and basis of design, space and use descriptions, single line drawings and schematics
for major systems, control drawings, sequences of control and a table of all set points
and implications of changing them, schedules, startup and shutdown.