Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 12/5/2018 - P20

Finance Committee - Agenda - 12/5/2018 - P20

By dnadmin on Mon, 11/07/2022 - 11:25
Document Date
Fri, 11/30/2018 - 13:06
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 12/05/2018 - 00:00
Page Number
20
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__120520…

City of Nashua Waste Water Treatment Facility —- Energy Recovery Generator Upgrade
Construction Administration

2 Scope of Work

Pre-Construction Services

Review General Contractor proposed schedule

Review Contractor bid and provide technical evaluation
Review Contractor Change Order Requests

Review Contractor Invoice

Review Contractor final completion

WP WN

Construction Observation

1. Attend bi-weekly construction meetings (up to 16)

2. Review construction progress schedule

3. Inspection construction for workmanship & accordance with plans & specs (up to 16
visits)

4. Participate punch list process

5. Perform a final walk thru with NWWTF and GC

Contractor Request for Information (RFD and Submittal Review
1. Review RFI (up to 18 RFI and 1 review cycle)
2. Review and assess contractor submittal (1 review cycle)

Startup and Commissioning

1. Develop ERU system startup and commissioning checklists

2. Develop Training Plans. Define minimum training requirement and skills that the
operation staff would be needed to operate the ERU properly and safely. Detailed
training plans and course materia! for the engine generator will be prepared by
others.

3. Waldron will conduct system operation trainings (up to 2 x 4 hour sessions).
Equipment training by others.

4, Provide technical inputs to NWWTF for Eversource interconnect testing. Utility and
major equipment startup technician coordination by NWWTF.

5. Perform Independent Review of Interconnection installation per Eversource
requirements, including managing project photo directory per requirements

6. Participate trouble shooting during startup and commissioning (up to 8 mandays on

site and 40 manhours remote support). GC and NWWTF to provide trade and

operation personnel to assist.

Participate Commissioning punch list and resolution.

8. Collect startup and completed checklists from Contractor as part of the project
turnover

9. Issue Commissioning Report.