STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
This agreement is made:
BETWEEN the OWNER: City of Nashua, New Hampshire
229 Main Street
Nashua, NH 03060-2019
And the CONTRACTOR: William P. Davis, Excavation LLC
and its successors, transferees and assignees
(together “CONTRACTOR”)
PO Box 758
Hampton, NH 03843
For the following Project: |_RFP1087-120916
Upgrade of Sewer System Siphon Covers
ARTICLE 1 —- THE CONTRACT DOCUMENTS
The CONTRACTOR shall complete the work described in the Contract Documents for this
project. The documents consist of:
L.
Z:
Aw SY
8.
This Agreement signed by the OWNER and CONTRACTOR, including the General
Terms and Conditions;
Exhibit B - RFP1087-120916, Upgrade of Sewer System Siphon Covers including
Addendum! issued November 28, 2016;
Exhibit C - Drawings and Specifications provided in the bid documents;
Exhibit D - Bid Table Submission dtd December 9, 2016;
Exhibit E - Payment and Performance Bonds;
Exhibit F - Insurance Certificate;
Written change orders for minor changes in the Work issued after execution of this
Agreement; and
Fully Executed OWNER Purchase Order
The Contract represents the entire and integrated agreement between the parties and supersedes
prior negotiations, proposals, representations or agreements, either written or oral. Any other
documents which are not listed in this Article are not part of the Contract.
In the event of a conflict between the terms of the Proposals and the terms of this Agreement, a
written change order and/or fully executed OWNER Purchase Order, the terms of this Agreement,
the written change order or the fully executed OWNER Purchase Order shall control over the
terms of the Proposals
Page 1 of 12