is
a>. «4,
WOODARD
& CURRAN
building and areas to be dehumidified or air-conditioned will also need to be finalized
during detailed design.
e. Safety: Design will meet or exceed any and all regulatory requirements for the safe
operation of a water booster station.
f. Instrumentation and Controls: Work with the Client to develop a conceptual process
instrumentation and control strategy, and integrate with the newly upgraded
Supervisory Control and Data Acquisition (SCADA) system.
g. Electrical: Provide a power conditioning uninterruptable power supply (UPS) with
monitoring signals installed and visible in SCADA.
h. Construction cost estimate (Estimate of Probable Costs).
4, Meet with the Client to deliver and discuss the 65% design. Incorporate comments and revisions
as part of the final design.
5. Develop 90%design plans and specifications for Client review including:
a. Final Drawings and Specifications
b. Updated Construction Cost (Estimate of Probable Costs)
6. Incorporate Client's final comments and deliver final design package.
ASSUMPTIONS
1. Scope of services does not include surveying or geotechnical investigations.
2. Anew electric service is not considered necessary at this time.
COMPENSATION
The Scope of Services will be completed for a total price of $105,600.00
Phase 1 — Design shall be billed hourly at the rates specified in the NH DES Contract, not to exceed
$105,600.00 This budget will not be exceeded without prior written authorization by the Client.
SCHEDULE
Woodard & Curran will complete the work for the above phase based on the following schedule:
Fon>
Preliminary Design Memo shall be completed within two months of the notice to proceed date.
65% design shall be completed within four months of the notice to proceed date.
90% design shall be completed within six months of the notice to proceed date.
Final design package shall be completed within eight months of the notice to proceed date if Client
provides final comments within 45 days of 90% design package delivery.
City of Nashua (228730.18) 2 Woodard & Curran
2016.12.13 Nashua Water Booster PS Proposal
R34
December 16, 2016