Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 2/1/2017 - P254

Finance Committee - Agenda - 2/1/2017 - P254

By dnadmin on Mon, 11/07/2022 - 10:29
Document Date
Wed, 02/01/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/01/2017 - 00:00
Page Number
254
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__020120…

CITY OF NASHUA, NEW HAMPSHIRE
WWTF HEADWORKS UPGRADE PROJECT
Change Order No. 2 Summary

Item No.

Description

Reason

Amount

Notes

Locker Replacement

City request to replace the remaining 30 lockers in the Men's Locker Room.

$14,199.93

T-Buck CP No.

1R-1, Dec. 5, 2016

Women's Shower Stall

City Building Department comments required the shower stall in the
Women's Locker Room be revised to an ADA-compliant unit.

$ 1,881.25

T-Buck CP No.

10, Dec. 1, 2016

Horn and Strobe Replacement

‘The existing Hazardous Gas Detector Horn and Strobe do not meet current
standards (are not explosion-proof). Relocation of the detector is part of this
project, and to complete this work the unit will need to be brought up to
code.

$ 11,073.75

T-Buck CP No.

12, Dec. 2, 2016

Wet Weill Ductwork

HVAC ducts in the Wet Well were damaged as a result of flooding; ducts
require replacement in order for the system to function properly.

$ 1,487.50

T-Buck CP No.

4, Dec. 16, 2016

Relocate 2-inch City Water

A 2-inch City Water line in the new Women's Locker Room needs to be
relocated to avoid a conflict with the new CMU wall being constructed as
part of the this project.

$ 1,987.38

T-Buck CP No.

6R-2, Dec. 21, 2016

Rain Leader Relocation

A 6-inch rain leader located in the corridor wall of the first floor requires
relocation as it will conflict with construction in the expanded Screenings
Room.

§ 9,029.00

T-Buck CP No.

8, Dec. 16, 2016

Install 3-inch Valve

City request to replace an existing 3-inch valve on the protected water line
located in the Boiler Room. Existing valve does not function properly; a new
valve is required to isolate the water line.

$ 2,906.74

T-Buck CP No.

9, Dec. 16, 2016

Hot Water Heater Feed

The existing power circuitry available was not compatible with the proposed
hot water heater installed in the Boiler Room.

$ 2,653.75

T-Buck CP No.

11, Dec. 2, 2016

Offset Odor Control Duct

There is a conflict between the new 30-inch odor control duct and an
existing 6-inch DIP generator drain; the duct will be off-set to avoid the
conflict.

$ 2,218.75

T-Buck CP No.

13A, Jan. 6, 2017

Total

$ 47,438.05 |