Section 01330 - Submittals
August 2016
Page 3 of 4
3066.07
B. CONTRACTOR shall complete all of the following items no later than the
specified number of calendar days. Associated shipping, work, and use of
materials by CONTRACTOR shall not begin until ENGINEER’s review of each
respective submittal is complete and where resubmission by CONTRACTOR is
not required by ENGINEER. ENGINEER shall reply to CONTRACTOR within 7
calendar days of receipt of each submittal and state whether or not
CONTRACTOR must resubmit.
Submittal
Due (Calendar Days)
Site Specific Health and Safety Plan.
10 days from the Notice
of Award
Construction Schedule. With Bid and every two
weeks during the
project.
Shop Drawings, Product Data and Samples, Material Specifications/ | 15 days prior to
Submittals related to but not necessarily limited to:
=" Wellheads;
" Nonwoven Geotextile;
® DrainTube™;
« Aggregate and soil materials;
= Wellhead assemblies;
« Isolation valve for the compressed air pipe;
= Well Caps;
«" Submersible pumps and appurtenances;
" HDPE pipe, fittings and appurtenances; and
" Corrugated metal pipe for road crossings.
placement and/or use.
Pipe pressure test report.
Within 7 days following
the test
Final Record Document Submittal.
No more than 14 days
from demobilization
from the site and prior
to application for final
payment.
Contractor’s Written Certification of Substantial Completion.
Prior to application for
final payment.
C. Submittals shall contain:
1. Date of submission;
2. Project title and number;
3. Names of:
a. Contractor
b. Manufacturer/Supplier;
Field dimensions, clearly identified as such;
DS
Identification of product, with specification section number;
Relation to adjacent or critical features of work or materials;
SANBORN HEAD