RESPONSIBILITIES
OWNER: City of Nashua
CONTRACTOR:
The following documents are attached to and made a part of this Certificate:
[For items to be attached see definition of Substantial Completion as supplemented and other specifically
noted conditions precedent to achieving Substantial Completion as required by Contract Documents.}
This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents
nor is it a release of CONTRACTOR’s obligation to complete the Work in accordance with the Contract
Documents.
Executed by ENGINEER on 20
(ENGINEER)
By:
(Authorized Signature)
CONTRACTOR accepts this Certificate of Substantial Completion on, 20
(CONTRACTOR)
By:
(Authorized Signature)
OWNER accepts this Certificate of Substantial Completion on 20
(For the City of Nashua)
By:
(Authorized Signature)
2 of 2
Certificate of Substantial Completion