3. In lieu of the releases or waivers of Liens specified in paragraph 14.07.A.2 and as approved by OWNER,
CONTRACTOR may furnish receipts or releases in full and an affidavit of CONTRACTOR that: (i) the releases
and receipts include all labor, services, material, and equipment for which a Lien could be filed; and (i) all
payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or
OWNER 's property might in any way be responsible have been paid or otherwise satisfied. If any Subcontractor
or Supplier fails to furnish such a release or receipt in full, CONTRACTOR may furnish a Bond or other collateral
satisfactory to OWNER to indemnify OWNER against any lien.
B. Review of Application and Acceptance
1. If, on the basis of ENGINEER's observation of the Work during construction and final inspection, and
ENGINEER's review of the final Application of Payment and accompanying documentation as required by the
Contract Documents, ENGINEER is satisfied that the Work has been completed and CONTRACTOR's other
obligations under the Contract Documents have been fulfilled, ENGINEER will, within ten days after receipt of
the final Application for Payment, indicate in writing ENGINEER's recommendation of payment and present the
Application for Payment to OWNER for payment. At the same time ENGINEER will also give written notice to
OWNER and CONTRACTOR that the Work is acceptable subject to the provisions of paragraph 14.09.
Otherwise, ENGINEER will return the Application for Payment to CONTRACTOR, indicating in writing the
reasons for refusing to recommend final payment, in which case CONTRACTOR shall make the necessary
corrections and resubmit the Application for Payment.
C. Payment Becomes Due
1. Thirty days after the presentation to OWNER of the Application for Payment and accompanying
documentation, the amount recommended by ENGINEER will become due and, when due, will be paid by
OWNER to CONTRACTOR.
14.08 Final Completion Delayed
A. If, through no fault of CONTRACTOR, final completion of the Work is significantly delayed, and if ENGINEER
so confirms, OWNER shall, upon receipt of CONTRACTOR's final Application for Payment and recommendation of
ENGINEER, and without terminating the Agreement, make payment of the balance due for that portion of the Work
fully completed and accepted. If the remaining balance to be held by OWNER for Work not fully completed or
corrected is less than the retainage stipulated in the Agreement, and if Bonds have been furnished as required in
paragraph 5.01, the written consent of the surety to the payment of the balance due for that portion of the Work fully
completed and accepted shall be submitted by CONTRACTOR to ENGINEER with the Application for such payment.
Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute
a waiver of Claims.
14.09 Waiver of Claims
A. The making and acceptance of final payment will constitute:
1. A waiver of all Claims by CONTRACTOR against OWNER other than those previously made in writing which
are still unsettled.
ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION
15.01 Termination, Abandonment, or Suspension at Will
The OWNER, in its sole discretion, shall have the right to terminate, abandon, or suspend all or part of the project and
contract at will. If the OWNER chooses to terminate, abandon, or suspend all or part of the project, it shall provide
CONTRACTOR 10 day’s written notice of its intent to do so.