Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 2/1/2017 - P188

Finance Committee - Agenda - 2/1/2017 - P188

By dnadmin on Mon, 11/07/2022 - 10:28
Document Date
Wed, 02/01/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/01/2017 - 00:00
Page Number
188
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__020120…

f. When both addition and credits are involved in any one change, the adjustment in CONTRACTOR's fee
shall be computed on the basis of the net change in accordance with paragraphs 12.01.C.2.a through
12.01.C.2.¢ inclusive.

12.02 Change of Contract Times

A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written Amendment. Any
Claim for an adjustment in the Contract Times (or Milestones) shall be based on written notice submitted by the party
making the claim to the ENGINEER and the other party to the Contract in accordance with the provisions of
paragraph 10.05.

B. Any adjustment of the contract Times (or Milestones) covered by a Change Order or of any Claim for an
adjustment in the Contract Times (or Milestones) will be determined in accordance with the provisions of this Article
12.

12.03 Delays beyond CONTRACTOR'S Control

A. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or
Milestones) due to delay beyond the control of CONTRACTOR, the Contract Times (or Milestones) will be extended
in an amount equal to the time lost due to such delay if a Claim is made therefore as provided in paragraph 12.02.A.
Delays beyond the control of CONTRACTOR shall include, but not be limited to, acts or neglect by OWNER, acts or
neglect of utility owners or other contractors performing other work as contemplated by Article 7, fires, floods,
epidemics, abnormal weather conditions, or acts of God.

12.04 Delays within CONTRACTOR's Control

A. The Contract Times (or Milestones) will not be extended due to delays within the control of CONTRACTOR.
Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the
control of CONTRACTOR.

12.05 Delays beyond OWNER's and CONTRACTOR'S Control

A. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or
Milestones) due to delay beyond the control of both OWNER and CONTRACTOR, an extension of the Contract
Times (or Milestones) in an amount equal to the time lost due to such delay shall be CONTRACTOR's sole and
exclusive remedy for such delay.

12.06 Delay Damages

A. In no event shall OWNER or ENGINEER be liable to CONTRACTOR, any Subcontractor, any Supplier, or any
other person or organization, or to any surety for or employee or agent of any of them, for damages arising out of or
resulting from:

1. Delays caused by or within the control of . CONTRACTOR; or
2. Delays beyond the control of both OWNER and CONTRACTOR including but not limited to fires, flood,
epidemics, abnormal weather conditions, acts of God, or acts or neglect by utility owners or other contractors
performing other work as contemplated by Article 7.
B. Nothing in this paragraph 12.06 bars a change in Contract Price pursuant to this Article 12 to compensate

CONTRACTOR due to delay, interference, or disruption directly attributable to actions or inactions of OWNER or
anyone from whom OWNER is responsible.

GC - 42 of 54