ARTICLE 7 - OTHER WORK
7.01 Related Work at Site
A. OWNER may perform other work related to the Project at the Site by OWNER’s employees, or let other direct
contracts therefore, or have other work performed by utility Owner’s. If such other work is not noted in the Contract
Documents, then:
1. Written notice thereof will be given to CONTRACTOR prior to starting any such other work; and
2. If OWNER and CONTRACTOR are unable to agree on entitlement to or on the amount or extent, if any, of any
adjustment in the Contract Price or Contract Times that should be allowed as a result of such other work, a Claim
may be made therefore as provided in paragraph 10.05.
B. CONTRACTOR shall afford each other contractor who is a party to such a direct contract and each utility
OWNER (and OWNER, if OWNER is performing the other work with OWNER’s employees) proper and safe access
to the Site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution
of such other work and shall properly coordinate the Work with theirs. Unless otherwise provided in the Contract
Documents, CONTRACTOR shall do all cutting, fitting, and patching of the Work that may be required to properly
connect or otherwise make its several parts come together and properly integrate with such other work.
CONTRACTOR shall not endanger any work of others by cutting, excavating, or otherwise altering their work and
will only cut or alter their work with the written consent of ENGINEER and the others whose work will be affected.
The duties and responsibilities of CONTRACTOR under this paragraph are for the benefit of such utility OWNERs
and other contractors to the extent that there are comparable provisions for the benefit of CONTRACTOR in said
direct contracts between OWNER and such utility OWNERs and other contractors.
C. If the proper execution or results of any part of CONTRACTOR’s Work depends upon work performed by others
under this Article 7, CONTRACTOR shall inspect such other work and promptly report to ENGINEER in writing any
delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and
results of CONTRACTOR’s Work. CONTRACTOR’: failure to so report will constitute an acceptance of such other
work as fit and proper for integration with CONTRACTOR’s Work except for latent defects and deficiencies in such
other work.
7.02 Coordination
A. If OWNER intends to contract with others for the performance of other work on the Project at the Site, the
following will be set forth in Supplementary Conditions:
1. The individual or entity who will have authority and responsibility for coordination of the activities among the
various contractors will be identified;
2. The specific matters to be covered by such authority and responsibility will be itemized; and
3. The extent of such authority and responsibilities will be provided.
B. Unless otherwise provided in the Supplementary Conditions, OWNER shall have sole authority and responsibility
for such coordination.
ARTICLE 8 - OWNER'S RESPONSIBILITIES
8.01 Communications to Contractor
GC - 32 of 54