28. Notice of Award--The written notice by OWNER to the apparent successful bidder stating that upon timely
compliance by the apparent successful bidder with the conditions precedent listed therein, OWNER will sign and
deliver the Agreement.
29. Notice to Proceed--A written notice given by OWNER to CONTRACTOR fixing the date on which the
Contract Times will commence to run and on which CONTRACTOR shall start to perform the Work under the
Contract Documents.
30. OWNER--The individual, entity, public body, or authority with whom CONTRACTOR has entered into the
Agreement and for whom the Work is to be performed.
31. Partial Utilization--Use by OWNER of a substantially completed part of the Work for the purpose for which
it is intended (or a related purpose) prior to Substantial Completion of all the Work.
32. PCB’s--Polychlorinated biphenyls.
33. Petroleum-- Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of
temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil,
petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and
crude oils.
34. Project--The total construction of which the Work to be performed under the Contract Documents may be
the whole, or a part as may be indicated elsewhere in the contract Documents.
35. Project Manual--The bound documentary information prepared for bidding and constructing the Work. A
listing of the contents of the Project Manual, which may be bound in one or more volumes, is contained in the
table(s) of contents.
36. Radioactive Material--Source, special nuclear, or byproduct material as defined by the Atomic Energy Act
of 1954 (42 USC Section 2011 et seq.) as amended from time to time.
37. Resident Project Representative--The authorized representative of ENGINEER who may be assigned to the
Site or any part thereof.
38. Samples--Physical examples of materials, equipment, or workmanship that are representative of some
portion of the Work and which establish the standards by which such portion of the Work will be judged.
39. Shop Drawings--All drawings, diagrams, illustrations, schedules, and other data or information which are
specifically prepared or assembled by or for CONTRACTOR and submitted by CONTRACTOR to illustrate some
portion of the Work.
40. Site--Lands or areas indicated in the Contract Documents as being furnished by OWNER upon which the
Work is to performed, including nghts-of-way and easements for access thereto, and such other lands furnished by
OWNER which are designated for the use of CONTRACTOR.
41. Specifications--That part of the Contract Documents consisting of written technical descriptions of
materials, equipment, systems, standards, and workmanship as applied to the Work and certain administrative
details applicable thereto.
42. Subcontractor--An individual or entity having a direct contract with CONTRACTOR or with any other
Subcontractor for the performance of a part of the Work at the Site.
43. Substantial Completion--The time at which the Work (or a specified part thereof) has progressed to the point
where, in the opinion of ENGINEER, the Work (or a specified part thereof) is sufficiently complete, in accordance