Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 2/1/2017 - P151

Finance Committee - Agenda - 2/1/2017 - P151

By dnadmin on Mon, 11/07/2022 - 10:28
Document Date
Wed, 02/01/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/01/2017 - 00:00
Page Number
151
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__020120…

Approved Shop Drawings and the reports and drawings of subsurface and physical conditions are not Contract
Documents. Only printed or hard copies of the items listed in this paragraph are Contract Documents. Files in
electronic media format of text, data, graphics, and the like that may be furnished by OWNER to CONTRACTOR
are not Contract Documents.

13. Contract Price--The moneys payable by OWNER to CONTRACTOR for completion of the Work in
accordance with the Contract Documents as stated in the Agreement (subject to the provisions of paragraph 11.03
in the case of Unit Price Work).

14. Contract Times--The number of days or the dates stated in the Agreement to: (i) achieve Substantial
Completion; and (ii) complete the Work so that it is ready for final payment as evidenced by ENGINEER’s written
recommendation of final payment.

15. CONTRACTOR--The individual or entity with whom OWNER has entered into the Agreement.
16. Cost of the Work--Sce paragraph 11.01.A for definition.

17. Drawings--That part of the Contract Documents prepared or approved by ENGINEER which graphically
shows the scope, extent, and character of the Work to be performed by CONTRACTOR. Shop Drawings and
other CONTRACTOR submittals are not Drawings as so defined.

18. Effective Date of the Agreement--The date indicated in the Agreement on which it becomes effective, but if
no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two
parties to sign and deliver.

19. ENGINEER--The individual or entity named as such in the Agreement.
20. ENGINEER’s Consultant--An individual or entity having a contract with ENGINEER to furnish services as
ENGINEER’ s independent professional associate or consultant with respect to the Project and who is identified as

such in the Supplementary Conditions.

21. Field Order--A written order issued by ENGINEER which requires minor changes in the Work but which
does not involve a change in the Contract Price or the Contract Times.

22. General Requirements--Sections of Division 1 of the Specifications. The General Requirements pertain to
all sections of the Specifications.

23. Hazardous Environmental Condition--The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous
Waste, or Radioactive Material in such quantities or circumstances that may present a substantial danger to

persons or property exposed thereto in connection with the Work.

24. Hazardous Waste--The term Hazardous Waste shall have the meaning provided in Section 1004 of the Solid
Waste Disposal Act (42 USC Section 6903) as amended from time to time.

25. Laws and Regulations; Laws or Regulations--Any and all applicable laws, rules, regulations, ordinances,
codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

26. Liens--Charges, security interests, or encumbrances upon Project funds, real property, or personal property.

27. Milestone--A principal event specified in the Contract Documents relating to an intermediate completion
date or time prior to Substantial Completion of all the Work.