GENERAL CONDITIONS
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in the Contract Documents and printed with initial or all capital letters, the terms listed below will
have the meanings indicated which are applicable to both the singular and plural thereof.
1. Addenda--Written or graphic instruments issued prior to the opening of Bids, which clarify, correct, or change
the Bidding Requirements or the Contract Documents.
2. Agreement--The written instrument which is evidence of the agreement between OWNER and CONTRACTOR
covering the Work.
3. Application for Payment--The form acceptable to ENGINEER which is to be used by CONTRACTOR during
the course of the Work in requesting progress or final payments and which is to be accompanied by such
supporting documentation as is required by the Contract Documents.
4, Asbestos--Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers
into the air above current action levels established by the United States Occupational Safety and Health
Administration.
5. Bid--The offer or proposal of a bidder submitted on the prescribed form setting forth the prices for the Work to
be performed.
6. Bidding Documents--The Bidding Requirements and the proposed Contract Documents (including all Addenda
issued prior to receipt of Bids).
7. Bidding Requirements--The Advertisement or Invitation to Bid, Instructions to Bidders, Bid security form, if
any, and the Bid form with any supplements.
8. Bonds--Performance and payment bonds and other instruments of security.
9. Change Order--A document recommended by ENGINEER which is signed by CONTRACTOR and OWNER
and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract
Times, issued on or after the Effective Date of the Agreement.
10. Claim--A demand or assertion by OWNER or CONTRACTOR seeking an adjustment of Contract Price or
Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services
by a third party is not a Claim.
11. Contract--The entire and integrated written agreement between the OWNER and CONTRACTOR
concerning the Work. The contract supersedes prior negotiations, representations, or agreements, whether written
or oral.
12. Contract Documents--The Contract Documents establish the rights and obligations of the parties and include
the Agreement, Addenda (which pertain to the Contract Documents), CONTRACTOR’s Bid (including
documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice of Award)
when attached as an exhibit to the Agreement, the Notice to Proceed, the Bonds, these General Conditions, the
Supplementary Conditions, the Specifications, the Drawings and the Purchases Order as the same are more
specifically identified in the Agreement, together with all Written Amendments, Change Orders, Field Orders, and
ENGINEER’s written interpretations and clarifications issued on or after the Effective Date Of the Agreement.