STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT is dated as of the day of in the year 2016 by and between the
City of Nashua, New Hampshire (hereinafter called OWNER) and
and its successors, transferees and assignees together hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:
ARTICLE 1 - WORK
1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
ARTICLE 2 - THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows:
The scheduled work for the Spring 2017 Landfill Gas System Expansion project consists of the installation of
new_horizontal gas collectors and liquid pumping systems in selected vertical wells in the active Phase I/II
Expansion Landfill.
ARTICLE 3 - ENGINEER
3.01 The Project has been designed by: Sanborn, Head & Associates
20 Foundry Street
Concord, NH 03301
who is hereinafter called ENGINEER and who is to act as OWNER's representative, assume all duties and
responsibilities, and have the rights and authority assigned to ENGINEER in the Contract Documents in connection
with completion of the Work in accordance with the Contract Documents.
ARTICLE 4 - CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final
payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Dates for Substantial Completion and Final Payment
A. The Work will be substantially completed within 90 calendar days of issuance of the “Notice to
Proceed”. Substantial completion is defined in paragraph 1.01.43 of the General Conditions. The Contract Times
commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment,
in accordance with paragraph 14.07 of the General Conditions, within 120 calendar days of issuance of the “Notice to
Proceed”.
4.03 Liquidated Damages
A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and that
OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 4.02 above, plus
AG -1 of 6