Bid Item No. 10 Survey
This item requires that CONTRACTOR provide all labor and equipment required to perform
construction layout and as-built documentation as required by Specifications. Construction
layout shall include vertical wells, gas collection trenches, connections to the existing LFG
conveyance pipe, and all other work items as defined in the Drawings and Specifications.
CONTRACTOR shall stake out alignments of the proposed pipe and locate and mark existing
LFG system features that may be encountered during construction, prior to the start of
excavation. As-built survey locations shall be performed as features are constructed for
payment and record information and shall include all completed items as defined in the
Drawings and Specifications. This item will be paid on a lump sum basis prorated over the
scheduled duration of the Work.
File No. 3066.07 4 of 4 October 2016