The following are the names and addresses of the emergency services or public transportation officials presumed to be
affected; however, the completeness of the list is not guaranteed.
Nashua Fire Department Nashua Police Department
70 East Hollis Street 0 Panther Drive
Nashua, NH 03060 Nashua, NH 03062
Telephone: (603) 594-3654 Telephone: (603) 594-3500
Attn: Chief Steven G. Galipeau Attn: Chief Andrew J. Lavoie
NH Department of Transportation Greenman-Pedersen, Inc.
Highway Maintenance District #5 181 Ballardvale Street, Suite 202
16 East Point Drive Wilmington, MA 01887
Bedford, NH 03110 Telephone: (978) 570-2999
Telephone: (603) 666-3336 Attn: John Osorio
Attn: Richard Radwanski Email: josorio@gpinet.com
City of Nashua Engineering Department 9 Riverside
Street
Nashua, NH 03062
Telephone: (603) 589-4700 Attn: Wayne
Husband
SECTION 106 — CONTROL OF MATERIAL
Amend Subsection 106.01, Source of Supply and Quality Requirements, with the following:
All materials installed under this Contract shall be listed on the NHDOT Qualified Products List as appropriate, unless
otherwise specified in these Construction Specifications. A list of materials proposed to be installed shall be provided
by the Contractor to the Engineer and the City.
Amend Subsection 106.03, Samples, Tests, Cited Specifications, with the following:
Material sampling and testing is to be in accordance with NHDOT procedure for progress and performance. Testing is
to be provided by the City as administered through the Engineer. The schedule of testing is to be established by the
Contractor in accordance with Section 106 of the NHDOT Specifications.
Additional testing required for the Contractor's information may be provided by the same testing agency but will be
at the Contractor's expense. The Contractor will be responsible for any charges to the City from the testing agent that
result from a delay in testing procedures after being scheduled due to ongoing construction operations or an
unprepared site.
See also Section 13.03 of the General Conditions for additional information.
Amend Subsection 106.06, Storage and Handling of Materials, with the following:
The Contractor shall not store equipment, construction vehicles, and materials within the clear zoned of the traveled
way. Location of storage areas within the right-of-way will be subject to the approval by the appropriate agency. The
Contractor shall maintain a clear travel-way for emergency vehicles and general access to abutting properties at all
times.
Construction Specifications.doc 8-4