To: Board of Aldermen
Filed With: Daniel Healey, City Clerk
From: Jim Donchess
Date: August 25, 2022
Re: Emergency PO Request — Boiler Replacement
Pursuant to 5-90 (G) of the NRO, | have authorized Emergency Purchase Order Request for the replacement
of a boiler for the Hunt Memorial Building in an amount of $89,900 to Palmer & Sicard Inc.
The boiler located at the Hunt Memorial Building recently failed inspection. Three
different vendors were contacted to get estimates for areplacement. Only Palmer &
Sicard submitted a proposal. A replacement boiler has an approximate lead time of 4-6
weeks. With chillier weather approaching it is critical that the boiler is purchased as
quickly as possible as providing heat is necessary to keep the Hunt Memorial Burlding
operational.
Thank you.