CHANGE ORDER
No. 1
PROJECT: 2022 Paving Program
EXECUTED CONTRACT DATE: March 22, 2022
DATE OF ISSUANCE:___Upon City Approval EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 170206
CONTRACTOR: Sunshine Paving Corporation
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
Increase Item 900 liquid asphalt adjustment from $125,000.00 to $250,000.00.
Justification:
Item 900 liquid asphalt adjustment is an allowance to account for the price increase or decrease of
liquid asphalt. The cost of the liquid asphalt is furnished by the NHDOT Bureau of Materials and
Research monthly. Over the course of the construction season the cost of this item has increased from
$625.00/ton (January 2022) to $800.00/ton (August 2022).
Attachments:
New Hampshire Monthly Fuel and Asphalt Prices (Page 1)
IFBO660-020922 2022 PAVING PROGRAM