COST OR PRICE SUMMARY FORMAT FOR SUBAGREEMENTS UNDER NH SAG & SRF
Form Approved
DES 02/06
PART I - GENERAL
1, GRANTEE / LOANEE
City of Nashua, New Hampshire
2. GRANT/LOAN NO.
3. NAME OF CONTRACTOR OR SUBCONTRACTOR
Woodard & Curran, Inc.
4. DATE OF PROPOSAL
December 16, 2016
5. ADDRESS OF CONTRACTOR OR SUBCONTRACTOR (Include ZIP)
6. TYPE OF SERVICE TO BE FURNISHED
PART II - COST SUMMARY
HOURLY ESTIMATED
7. DIRECT LABOR (Specify labor categories) HOURS RATE COST TOTALS
Client Manager , 18 $82.00 $1,476.00
Project Manager 64 $57.00 $3,648.00
Lead Project Engineer 148 $37.00 $5,476.00
Sr. Technical Advisor 16 $82.60 $1,312.00
SCADA Engineer 60 $45.00 $2,700.00
Sr. Electrical Engineer 12.5 Ae WE $713.00
Electrical Engineer 10 |: $37.00 $4,070.00
Staff Engineer 211 $27.00 $5,697.00
Sr. Structural Engineer ie $57.00 $456.00
Structural Engineer 60 $37.00 $2,220.00
Cost Estimator 24 $49.00 $1,176.00
Technical Specialist HVAC 40 $46.00 $1,840.00
Project Specialist 30 $28.00 $840.00
$31,624.00
ae aa ESTIMATED
8. INDIRECT COSTS (Specify indirect cost pools) os RATE X BASE = COST
woe 2.02 $31,624.00 $64,226.00
INDIRECT COSTS TOTALS: $63,881.00
9. OTHER DIRECT COSTS Ee 4
a. TRAVEL re ESTIMATED
a COST
(1) TRANSPORTATION $545.00
(2) PER DIEM se
TRAVEL COSTS TOTAL: $545.00
b. EQUIPMENT, MATERIALS, SUPPLIES ESTIMATED
(Specify categories) QTY COST COST
EQUIPMENT SUBTOTAL:
c. SUBCONTRACTS ESTIMATED
COST
|
SUBCONTRACTS SUBTOTAL:
d. OTHER (Specify categories) ESTIMATED
COST
OTHER SUBTOTAL:
e. OTHER DIRECT COSTS TOTAL: $545.00
10. TOTAL ESTIMATED COST $96,050.00
11. PROFIT $9,550.00
$105,600.00
12. TOTAL PRICE
Page 1 of 2