Finance Committee - Agenda - 3/15/2017 - P83

By dnadmin on Mon, 11/07/2022 - 10:27
Document Date
Wed, 03/15/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/15/2017 - 00:00
Page Number
83
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__031520…

CHANGE ORDER

No. 3
PROJECT: 2014 Four Hills Landfill Residential Setback Barrier Wall Construction
OWNER’S CONTRACT NO: IFB0593-050514
DATE OF ISSUANCE: March 16, 2017 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: TBD
CONTRACTOR: Northeast Earth Mechanics, Inc.

ENGINEER; «Sanborn Head Associates

You are directed to make the following changes in the Contract Documents: Description, Purpose of Change Order,
and Justification. Attachments: (List Documents supporting change)

Purpose: Additional Work for the Setback Barrier Wall.
Attachment: Northeast Earth Mechanics, Inc. proposal dated Jan 16, 2017
Description: For initial construction of the eastern setback barrier wall, and continued construction of the western

setback wall te an elevation 268 feet. To construct the eastern setback wall, establish the compacted soil foundation
over the primary liner drainage sand and place concrete waste blocks on the foundation up to elevation 258 feet.

New Price and Time Summary:

CHANGE IN CONTRACT PRICE:

Original Contract Price

$163,727

CH E IN CONTRACT TIMES:
Original Contract Times

Ready for final payment: September 10, 2014
days or dates

Net changes from previous Change Orders

$328,252

Net change from previaus Change Orders

Substantial Completion: 785 days
Fina) Completion: 815 days

Contract Price prior to this Change Order

$491,979

Contract Times prior to this Change Order

Ready for final payment: December 15, 2016
days or dates

Net Increase (decrease) of this Change Order

$291,932

Net Increase (decrease) of this Change Order

Substantial Completion: 335 days
Final Completion: 365 days

Contract Price with all approved Change Orders

$783,911

Contract Times with afl approved Change Orders

Ready for final payment: December 15, 2017
days or dates

RECOMMENDED: APPROVED:

ee Utd Kad ten. By:
Supertat (Authoriztd Signature) Owner (Authorized Signature)

Date: 3-1-2601 [

Date:

Change Order #3
2014 Setback Barrier Wall

ACCEPFED:

By:
ContractorfAuthorized Signature)

Date: 7-2 ~do/7

Page Image
Finance Committee - Agenda - 3/15/2017 - P83