Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/15/2017 - P82

Finance Committee - Agenda - 3/15/2017 - P82

By dnadmin on Mon, 11/07/2022 - 10:27
Document Date
Wed, 03/15/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/15/2017 - 00:00
Page Number
82
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__031520…

Change Order #2 in the amount of $164,340 continued construction of the
western wall into the Phase II/Stage II landfill up to an elevation of 260 feet.

Change Order #3 in the amount of $291,932.00 will allow for initial construction
of the eastern setback barrier wall, and continued construction of the western
setback wall to an elevation 268 feet. To construct the eastern setback wall, NEM
will have to establish the compacted soil foundation over the primary liner
drainage sand and place concrete waste blocks on the foundation up to elevation
258 feet.

It is the recommendation of the Solid Waste Superintendent to continue
construction of the Set Back Barrier Wall with NEM. They have provided
reasonable, consistent pricing and quality construction services for each
completed phase of this project. Upon approval of Change Order #3 the total
cost of the contract is $783,911.