CERTIFICATE OF SUBSTANTIAL COMPLETION
Owner Project No. —1IFBO779-071422 Engineer Project No. 90006-034
Project: Siphon Rehabilitation Project
Contractor:
Contract For: Siphon Rehabilitation Contract Date:
This Certificate of Substantial Completion applies to all work under the Contract Documents or to the following specified
parts thereof:
To
(Owner)
And to
(Contractor)
The Work to which this Certificate applies has been inspected by authorized representatives of OWNER, CONTRACTOR
and ENGINEER, and that Work is hereby declared to be substantially complete in accordance with the Contract
Documents on Documents on
(Date of Substantial Completion)
A tentative list of items to be completed or corrected is attached hereto. This list may not be all-inclusive, and the failure
to include an item in it does not alter the responsibility of CONTRACTOR to complete all the work in accordance with the
Contract Documents. The items in the tentative list shall be completed or corrected by CONTRACTOR within
calendar days of the above Substantial Completion.
The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat, utilities,
insurance and warranties shall be as follows:
RESPONSIBILITIES:
OWNER:
CONTRACTOR:
The following documents are attached to and made a part of this Certificate:
Page 11 of 15