NOTICE TO PROCEED
Dated , 20
TO:
(Insert Name of Contractor as it appears in the Bid Documents)
ADDRESS:
OWNER’S PROJECT NO. N/A
PROJECT: Siphon Rehabilitation Project
OWNER’S CONTRACT NO. __IFBO779-071422
CONTRACT FOR: Siphon Rehabilitation Project
You are notified that the Contract Time under the above contract will commence to run on , 20
By that date, you are to start performing your obligations under the Contract Documents. In accordance with paragraph 3
of the Agreement, the dates of Substantial Completion and Final Completion are , 20
and ,20___ respectively.
Before you may start any Work at the site, paragraph 27 of the General Conditions provides that you and Owner must
each deliver to the other (with copies to ENGINEER) certificates of insurance which each is required to purchase and
maintain in accordance with the Contract Documents. Also before you may start any Work at the site, you must:
Copy to ENGINEER
(Use Certified Mail, return receipt Requested) OWNER:
By:
(Authorized Representative)
NAME:
(Title)
ACKNOWLEDGEMENT OF NOTICE
Receipt of the above NOTICE TO PROCEED is hereby acknowledged by:
(Contractor)
This the , day of 20_, by
Employee Identification Number:
Page 9 of 15