Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/17/2017 - P385

Finance Committee - Agenda - 5/17/2017 - P385

By dnadmin on Mon, 11/07/2022 - 10:26
Document Date
Wed, 05/17/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/17/2017 - 00:00
Page Number
385
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051720…

ASTM F 1743: Rehabilitation of Existing Pipelines and Conduits

by Pulled-in-Place Installation of Cured-in-Place
Thermosetting Resin Pipe (CIPP)

* (Note: The Contractor may substitute an alternative method other than by
inversion to install the liner, as approved by the Engineer.

1.03 QUALITY ASSURANCE

A. REQUIREMENTS

1.

Products used in the work of this section shall be produced by manufacturers
regularly engaged in the manufacture of cured-in-place liners for municipal
wastewater systems and with a history of successful production acceptable to
the owner.

The installing Contractor shall be licensed by the cured-in-place lining system
manufacturer and shall have successful experience in the installation of cured-
in-place lining systems in municipal wastewater systems. The Contractor shall
also be familiar with the specified requirements and the methods needed for
proper performance of the work of this section.

. When requested by the owner, the Contractor shall submit evidence acceptable

to the owner, such as a certified copy of a license or agreement, that it has the
authority to use and/or install the liner product.

The finished liner shall be continuous over the entire length of the liner
insertion run between the manholes and shall be free from visual defects such
as foreign inclusions, dry spots, pinholes, and delamination.

Wrinkles in the finished liner pipe which cause a backwater of one inch or
more or reduce the hydraulic capacity of the pipe are unacceptable and shall be
removed or repaired by the Contractor. If a void between the wrinkle and the
pipe develops, the Contractor shall repair or replace that section of the pipe.
Methods of repair shall be proposed by the Contractor and submitted to the
owner for review.

Following sewer cleaning and prior to installation of liner and finish work at
the manholes, the sewer shall be televised and recorded on videotape or in
digital format acceptable to the Engineer such as CD or DVD, and shall be
provided to the Engineer. The Contractor shall also televise the sewer after
completion of all liner insertion and finish work at the manholes. All Closed-
Circuit Television (CCTV) work is to be completed per a national standard for
sewer inspections.

02650-2