SECTION 02441
CLEANING, TELEVISION INSPECTION, AND TESTING OF NEW PIPELINES
PART 1 - GENERAL
1.01
A.
1.02
1.03
1.04
WORK INCLUDED:
The Contractor shall furnish all materials, tools, labor and equipment necessary to visually
inspect by means of a closed-circuit television all gravity sewers installed under this
Contract, as hereinafter specified. The sewers shall be inspected throughout their entire
length. The Contractor shall also test all joints throughout the entire length of installed
sewer.
RELATED WORK:
Section 01330, SUBMITTALS
Section 01331, DOCUMENTATION
Section 02085, POLY VINYL CHLORIDE GRAVITY PIPE AND FITTINGS
QUALITY ASSURANCE:
The work described herein shall be performed by a company with not less than five years of
experience in providing the required services, employing experienced workers and
experienced supervisory personnel. Supervisory personnel shall have not less than three
years of experience in providing the required services and shall be present at the jobsite
during all work related to the required services.
SUBMITTALS: IN ACCORDANCE WITH REQUIREMENTS OF GENERAL
SPECIFICATIONS, SUBMIT THE FOLLOWING:
Prior to beginning work, submit six (6) sets of the following:
1. Qualifications of the firm/personnel who will perform the work;
2. Description of system proposed for handling existing flows during the various
procedures to be carried out;
3. Description of the system and equipment proposed for cleaning;
4. Description of the system and equipment proposed for televising the pipe after
cleaning; and
5. Description of the system and equipment proposed for testing the joints.
02441-1