After large areas of Asbestos-Containing Materials have been fully wetted and
tested, the asbestos shall be carefully removed in small sections by hand using
suitable tools
As the material is removed, it shall be promptly wetted and packed into Disposal
Bags and/or approved disposable drums. When each bag 1s full, the packaged
material shall be sprayed with amended water, sealed, and transported to a
temporary storage area inside of the Work Area. Accumulations of standing or
free water shall not be allowed to collect on the Work Area floor or ground.
The Asbestos Abatement Contractor shall continuously mist the Work Area and
spray the material to prevent it from drying out and to reduce airborne dust and
fiber levels.
Once the majority of the Asbestos-Containing Material 1s removed, the Asbestos
Abatement Contractor shall remove all remaining visible and microscopically
detectable material using appropriate tools.
The Asbestos Abatement Contractor shall minimize contamination of the ground,
the excavation floor, the exterior of Disposal Bags and containers, and all other
surfaces within the Work Area. At the end of each shift, all surfaces shall be
cleaned of all materials and then HEPA-vacuumed or wet cleaned and all debris
packaged in Disposal Bags.
Excessive water accumulation or flooding in the Work Area shall require Work to
stop until the water 1s collected and disposed of properly.
Should the Contractor remove any non-friable Asbestos-Containing Materials in a
manner which transforms the material into a friable condition, the Contractor shall
be responsible for handling and disposing of this material as friable Asbestos-
Containing Waste Material.
Disposal of all Asbestos-Containing Material shall be in accordance with
Subsection 3.08.
Upon notification by the Engineer that the level specified in Subsection 3.10.F has
been exceeded, the Contractor shall immediately cease Asbestos Abatement
Activities until the fault 1s corrected. Work shall not recommence until
authorized by the Engineer.
ASBESTOS REMOVAL WITHOUT CONTAINMENT
This Subsection 1s provided for removal of asbestos-containing materials 1n excavation
areas where the use of containment structures is not possible. The Contractor shall
submit detailed procedures to the Engineer prior to performing any asbestos abatement
02111-35