1.13
Fire Extinguishers: The Contractor shall locate comply with the applicable
recommendation of NFPA Standard 10 "Standard For Portable Fire Extinguishers." The
Contractor shall locate fire extinguishers where they are most convenient and effective
for their intended purpose, but provide no less than one extinguisher in each Work Area,
in Equipment Room, and one outside Work Area in Clean Room.
PERSONNEL PROTECTION
The Contractor shall provide personnel protection as required by all applicable
regulations.
Respirators, disposable coveralls, head covers, and footwear covers shall be provided by
the Contractor for the Engineer and other authorized visitors who may inspect the job
site.
The Contractor shall require that workers NOT eat, drink, smoke, chew gum or tobacco,
or use toilet facilities (either existing or temporary) in Work Areas and Regulated Areas.
To eat, chew, drink or smoke, workers shall dress in street clothes before entering the
non-Work Areas of the building.
The Contractor shall post written procedures near the Work Area and train all personnel
on the procedures for the evacuation of the injured and the handling of potential fires.
Provide aid to a seriously injured worker without delay for decontamination. Make
provisions to minimize exposure of rescue workers and to minimize spreading of
contamination during evacuations and fire procedures.
The Contractor shall instruct all employees and workers in the proper care of their
personally issued respiratory equipment, including daily maintenance, sanitizing
procedures, and personal decontamination procedures to be utilized upon leaving the
Work Area or Regulated Area.
PART 2 PRODUCTS
2.01
GENERAL REQUIREMENTS
The Contractor shall deliver all materials and equipment to the site in the original
containers bearing the name of the manufacturer, and details for proper storage and
usage.
All materials or equipment delivered to the site shall be unloaded, temporarily stored,
and transferred to the Regulated Area or Work Area in a manner which shall not
interfere with building operations.
Unloading and temporary storage sites, and transfer routes, must be reviewed in advance
by the Engineer.
02111-22