1.06
information. When such events are known or predictable in advance,
advise the Engineer in advance at earliest possible date.
b. Reporting Accidents: Prepare and submit reports of significant accidents,
at site and anywhere else work is in progress. Record and document data
and actions; comply with industry standards. For this purpose, a
significant accident 1s defined to include events where personal injury 1s
sustained, or property loss of substance is sustained, or where the event
posed a significant threat of loss or personal injury.
3. Contingency plan. For content see Subsection 1.04.B.5
4. Notifications to other entities at job site. Comply with hazard communication
requirements as set forth in 29 CFR 1926.1101. Notify other entities that may be
affected by the Work as directed by the Engineer.
SCHEDULES AND REPORTS
Coordination: Coordinate both the listing and timing of reports and activities required
by provisions of this Section with other Sections of this specification. Make appropriate
distribution of each report to all parties involved in the Work including the Engineer.
For all Work specified in this Section, the Contractor shall provide a proposed detailed
schedule including work dates, work shift time, number of employees, dates of start and
completion including dates of preparation work, start and completion of ACM removal
and final inspection dates for all areas and types of ACM as described in the
Specifications.
Daily Construction Reports: For all Work specified in this Section, the Contractor shall
prepare a daily construction report, recording the following information concerning
events at the site; and submit duplicate copies to the Engineer at weekly intervals:
List of subcontractors at the site.
Accurate count of personnel at the site.
High and low temperatures, general weather conditions.
Personal air monitoring results.
Accidents and unusual events.
Meetings and significant decisions.
Stoppages, delays, shortages, losses.
Meter readings and similar recordings.
Emergency procedures.
Orders and requests of governing authorities.
Change Orders received, implemented.
Services connected, disconnected.