A contingency for coordination with the Railroad company at Temple St is
provided to cover such costs as Railroad Flaggers. This contingency is provided
as an allowance in Item 11.
NOTE: THE CONTINGENCY DOES NOT COVER THE COSTS
ASSOCIATED WITH THE RAILROAD INSURANCE REQUIRMENTS.
THOSE ARE COVERED UNDER ITEM 1K(1) AS OUTLINED ABOVE.
A contingency for contaminated soil excavation and disposal is provided by the
allowance Item 11a.
Temporary removal and resetting of stop signs or similar will be paid by Item 8j.
Pre-con sewer videos are required is some streets as shown in the drawings.
While videos on lining streets are subsidiary, those on pipe replacement will be
paid by the Item 12 series. Contractor shall follow all the same video
requirements set forth on the lining streets.
Adjustment and Replacement of MH frames/covers and catch basin frames/grates
is required on occasional structures that do not call for complete new structure. In
this case, Items 3b, 3c and 3d apply. Note, on replacement of units, the
replacement item also includes adjustment.
Root cutting will be paid under Items 2s.
Manhole lining will be done per specification section 02800 and will be paid
by vertical foot only (regardless of diameter using Item lo.
Manhole invert lining will be paid by Item 1p. Contractor shall submit technical
specifications for the Engineer’s review.
END OF SECTION
01150 - 24