The unit price shall include full compensation for all materials, equipment and
labor necessary to install the vertical granite curbing to the details shown in the
plan set. Compensation will include placement of small amount of backfill
material on the backside of the granite curbing such that it will minimize the
tripping hazard if it rises more than 2 above the existing grade.
Vertical curbing shall be installed at new handicap ramps where there is no
existing curbing at locations shown on the plan set. No extra payment will
allowed for granite curbing used in handicap ramp construction including curved
pieces when used at handicap ramps.
The work shall be paid for at the contract unit price per Linear Foot for Item 6j
Install Vertical Granite Curbing
I. AND REPLACE 4” CONCRETE SIDEWALK, 2"
BITUMINOUS CONCRETE SIDEWALKS OR BRICK
SIDEWALKS:
The removal of the existing sidewalk and driveways and placement of new
sidewalk and driveways shall be measured per square yard and shall include
furnishing and placement of material as shown on the plans or as ordered by
the Engineer. Sidewalks and driveways damaged by the contractor shall be
replaced at no cost to the city.
The unit prices under the appropriate subdivisions of this item shall constitute full
compensation for installing bituminous and/or concrete sidewalk, complete in
place, as necessary for removal, saw-cutting of adjacent sidewalk panels,
replacement, all gravel base materials, all hardware necessary and all work
incidental thereto and not specifically included for payment under other items.
Handicap ramps shown on the plan set shall all be constructed according to the
provisions of this pay item without additional payment should it require additional
work in constructing the handicap ramp.
The work shall be paid for at the contract unit price per Square Yard for Item 6k -
4" Concrete Sidewalks, Item 6k(1) - 6" Concrete Driveways and Item 6] - 2”
Bituminous Concrete Sidewalk. Brick Sidewalk work will be paid by Item 60.
HOT BITUMINOUS PAVEMENT, HAND METHOD
Hot Bituminous Pavement, Hand Method shall be measured per Ton and shall
conform to Section 403 of the NHDOT Standard Specifications and Specification
Section 02745, PAVING and shall include furnishing and placement of material
as shown on the plans or as ordered by the Engineer.
01150 - 17