Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/17/2017 - P240

Finance Committee - Agenda - 5/17/2017 - P240

By dnadmin on Mon, 11/07/2022 - 10:25
Document Date
Wed, 05/17/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/17/2017 - 00:00
Page Number
240
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051720…

IFB0779-041217
2017 SEWER REPLACEMENT PROGRAM

ARTICLE 17 -- MISCELLANEOUS

ADD the following to paragraph 17.07A:
SC-17.07 Road Closures and Traffic Delays

5. The CONTRACTOR is responsible for obtaining the City official “No On-Street
Parking” signs when needed. These signs are available at the City Engineering Office.
At the completion of work, the signs shall be removed and returned to the City in good
condition.

SC-17.10 Coordination with other parties:

CONTRACTOR is expected to work with the City to address minor drainage issues in
existing roadways. Resolution to drainage issue can entail shimming, milling, and/or
modifications to proposed road treatment.

It is anticipated that the gas and water companies will be replacing sections of their
existing lines either before or upon completion of the Sewer and Water replacement
projects. The contractor shall cooperate fully with that work.

SC-17.11 Winter Shutdown Period:

The CONTRACTOR only has permission to work into the winter conditions by the date
set on the street opening permit. In general, all work must shutdown for winter
conditions from December 31“ to April 15"". Only in unusual circumstances and by
permission from the City Engineer will the contractor be permitted to work from January
1* to April 1st, even if mild winter conditions persist.

SC - 2 of 2