Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/17/2017 - P177

Finance Committee - Agenda - 5/17/2017 - P177

By dnadmin on Mon, 11/07/2022 - 10:25
Document Date
Wed, 05/17/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/17/2017 - 00:00
Page Number
177
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051720…

STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR

THIS AGREEMENT is dated as of the day of in the year 2017 by and between the City of
Nashua, New Hampshire (hereinafter called OWNER) and and
its successors, transferees and assignees together hereinafter called CONTRACTOR).

OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:
ARTICLE 1 - WORK

1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
ARTICLE 2 - THE PROJECT

2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally
described as follows:

The scheduled work for the 2017 Sewer Replacement Program consists of work on Elm St, West Pearl St. Green St
Beard St. Monroe St. Terrace St. Warren St. Jackson St. Lowell St, Main St, Franklin St. and Mulberry St. Work
includes 260 feet of 8 to 10 inch PVC Sewer, 1620 feet of 12 inch PVC sewer, 880 feet of 15 inch PVC sewer, 600 feet

of 24 inch PVC sewer, 150 vertical feet of 4 foot diameter man hole, 16 feet of 4 foot diameter doghouse sewer man
hole, 550 feet of 12 inch CIPP lining, 500 feet of 15 inch CIPP lining, 430 feet of 18” ege shaped pipe CIPP lining, 64
feet of short liner point repair, 120 vertical feet of manhole lining, 1380 feet of sewer service connections, 1165 feet of
drain pipe. 120 vertical feet of sewer chimney, 5650 cubic yards of crushed gravel. 3000 tons of base paving, 970 tons
of top course paving, 1210 tons of temporary paving, 2300 feet of granite curb resetting, 1070 square yards of sidewalk
and driveway reconstruction, 30 feet of asbestos pipe removal. 3400 feet of 4 inch striping. 3330 feet of 12 inch
thermoplastic paint lines. possible asbestos and other contaminated material excavation and disposal. dye testing
approximately 90 service connections, 1110 feet of sewer videos of non-CIPP pipes and miscellaneous other sewer and
paving items.

ARTICLE 3 - ENGINEER
3.01 The Project has been designed by: Division of Public Works
Engineering Department
9 Riverside St
Nashua, NH 03062
who is hereinafter called ENGINEER and who is to act as OWNER's representative, assume all duties and

responsibilities, and have the rights and authority assigned to ENGINEER in the Contract Documents in connection
with completion of the Work in accordance with the Contract Documents.

ARTICLE 4 - CONTRACT TIMES
4.01 Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final
payment as stated in the Contract Documents are of the essence of the Contract.