127
IFB0779-041217
2017 Sewer Replacement Program
City of Nashua, New Hampshire
Division of Public Works
2017 Sewer Project
SUMMARIZED
6s 40 SY Removal of 6" Thick Concrete Under Pavement _
7a 1 LS Mobilization
8a 1 Allowance Police Officers _ $92,000.00 _ $92,000.00
8b 1 Allowance F lagmen _ $72,000.00 _ $72,000.00
8c 1 LS Maintenance of Traffic
8d 140 EA
8e 2,300 LF
8f 1,100 LF
8g 3,330 LF 12" Retroreflective White ThermoplasticLines
8i 1 EA Signal Detector Loops
8) 1 EA Remove and Reset Stop Sign
9a 1 Allowance Asphalt Cement Cost Adjustment _ $18,000.00 _ $18,000.00
Ob 140 Hr Night Crew
9c 1 Allowance Asbestos Material Removal Disposal $25,000.00 _ $25,000.00 _
10 90 EA Dye Testing Connections