To:
From:
Re:
F. Motion:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: April 20, 2017
Stephen Dookran, P.E., City Engineer
Engineering Department
2017 Sewer Rehabilitation Project
Construction
To approve the award of the construction contract for the 2017 Sewer Rehabilitation
Project to DeFelice Corporation of Dracut, MA in the amount of $3,255,683.30.
Funding will be through: Department: 169 Wastewater; Fund: Wastewater; Activity:
Sewer Rehab.
The annual sewer program addresses failing, aged sewers and associated structures and
piping. This 2017 Sewer Rehabilitation Project is expected to replace or line
approximately 1.1 miles feet of sewer mains located in the following streets:
Beard St (Fletcher St to 5 Beard St)
Elm St (West Pearl St to West Hollis St)
Elm St (Kinsley St to 96 Elm St)
Franklin St (from Front St to Main St)
Green St (Winter St to Franklin St)
Jackson St
Lemon St
Lowell St (from 32 Lowell St to 42 Lowell St)
Main St (from Medical Center Dr to Prospect St)
Main St localized repairs (from Allds St to Montgomery Ave)
Monroe St (58 Monroe St to Lake St)
Mulberry St (Chestnut St to Walnut St)
West Pearl St (Walnut St to 123 West Pearl St and intersection of Main St)
Temple St (from Commercial St to Amory St)
Terrace St
Warren St
Work includes replacing sewer service lateral connections to the right-of-way as well as
catch basins and manholes prior to road restoration. Some of the locations will require
the commitment of the utility companies for timely construction. Coordination issues
with abutters and school activity may impact the construction schedule.
Seven contractors attended the mandatory pre-bid meeting on March 22. Three bids
were received on April 12 as follows:
DeFelice Corporation of Dracut, MA $3,255,683.30
S.U.R Construction West, Inc of Winchester, NH $3,672,263.50
Cardillo & Son, Inc of Wakefield, MA $3,846,005.00