KF, CONTRACTOR does not consider that any further examinations, investigations, explorations, tests,
studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in
accordance with the other terms and conditions of the Contract Documenis.
G. CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the
Site that relates to the Work as indicated in the Contract Documents.
H. CONTRACTOR has correlated the information known to CONTRACTOR, information and
observations obtained from visits to the Site, reports and drawings identified in the Contract Documents and all
additional examinations, investigations, explorations, tests, studies, and data with the Contract Documents.
1. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or
discrepancies that CONTRACTOR has discovered in the Contract Documents, and the written resolution thereof by
ENGINEER is acceptable to CONTRACTOR.
J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.
ARTICLE 8 - CONTRACT DOCUMENTS
8.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement;
2. General Conditions; .
3. Supplementary Conditions;
4, Bid Bond;
5. Bid Form;
6. Performance Bond;
7. Payment Bond;
8. Certificate of Insurance
9. Technical Specifications as listed in Table of Contents
10. Addenda (numbers 1 to 3 _, inclusive);
11. Exhibits, as listed in the Table of Contents, to this Agreement
12. The following which may be delivered or issued on or after the Effective Date of the Agreement
and are not attached hereto:
a. Written Amendments
“AG -40f6