One flooring change order was submitted, the Trustees final carpet selection was more expensive than
the original specification. Cost: $1530
One drywall change order was submitted after unexpected mechanical systems under the floor resulted
in a need to change the layout of the fixtures. Cost: $3464
One change order was submitted related to additional acoustical ceiling tile at the tops of the new
column covers. Cost: $1700
One painting change order was submitted due to changes in paint colors and scope of painting at the
request of the Library and the Trustees. Cost: $3762
The total cost of all submitted change orders is $38,293, bringing the total contract cost to $478,876.
This falls within the original established construction budget of $486,790 approved by the Board of
Trustees in September, 2016 which is being paid for entirely by Trust funds.